1. The process of determining who needs what information, when they need it, and how it will be given to them is:
A. Information distribution
B. Communications requirements
C. Communications planning
D. Communications management
Which of the following is not a technology factor that may affect the project communications plan:
A. Immediacy of the need for the information
B. Length of the project
C. Expected project staffing
D. Logistics of how many individuals will be involved with
A. Status reporting
B. Progress reporting
C. Forecasting
D. Benchmark reporting
A. Cost estimating
B. Organizational planning
C. Cost budgeting
D. Performance reporting
A. Scope management
B. Production
C. Labor and materials
D. Project plan execution
Which tool and technique integrates scope, cost and schedule in measuring project performence?
A. Variance analysis
B. Earned value
C. Trend analysis
D. Performance report
Qustions 1:
1. In a weak matrix organization, functional managers are usually responsible for:
Monitoring personnel performance
Approval for changes to the project schedule
Monitoring their project team member’s deliverables
Changes that impact their team member~ participation
Qustions 3: