Qustions 1: 
According to McGregor, a manager who uses Theory X sees workers as-- 

a.  Highly motivated,willing to take responsibility, and reliable 
b. Highly untrustworthy, needing to be watched and closely managed at all times 
c. Very productive when first given an assignment 
d. Unproductive at first, followed by periods of high productivity 

Qustions 3:

A Project management information system comprises--

a.  Any of the project management software used for schedule development 
b. All the requited reports to be prepared on the project, who receives each one, and the method of distribution 
c. The policies and procedures to follow as the project is performed 
d. The tools and techniques used to gather, integrate, and disseminate the output of the other project management processes 

Qustions 5:

The Project plan should be distributed to--

a. All stakeholders in the performing organization
b. All project stakeholders 
c. Project team members and the project sponsor 
d. Those people defined in the communication management plan 

Qustions 2: 
Although an output of the various control processes, corrective action is also an input to project plan execution because it-- 

a. Ensures that project objectives are met 
b. Expedites actions to ensure that activities are completed on time 
c. Completes the feedback loop needed to ensure effective project management 
d. Involves performing a planned reponse for a specific project risk event 

Qustions 4:

A change control board is --

a. Recommended for use on all projects, large or small 
b. Used as required to approve or reject change requests 
c. Managed by the project manager who serves its secretare 
d. Composed of key members of the project team 

Qustions 6:

Leadership and management are both necessary on projects. One definition of managing is that it involves producing key results expected by stakeholders, whereas leadership involves -- 

a. Establishing direction, aligning people, and motivating and inspiring others 
b. Getting things done through other people 
c. Using charismatic power to motivate others to be productive 
d. Using all types of power, as appropriate, as motivational tools

下一篇:砺志PMP模拟题每周精选1

Qustions 1:
The purpose of project plan development is to--

a. Creat a document to guide project execution and control
b. Document project assumptions and contraints
c. Promote communication among stakeholders
d. Define key project reports

Qustions 2:

Overall change control is primarily concerned with-

a. Influencing factors that cause change, determining that change has occurred, and managing actual changes as...[查看详情]

  影视动画培训   北大BEC培训官方报名网站   2008美国夏令营启航官方指定报名网站   2008留学第一站!  
  北师大 火星时代
共举影视动画培训之鼎
  北大BEC培训官方报名网站
现在报名独享95折!
  2008年国家职业资格考试
一次过关完全备考手册
  2008留学第一站
留学资讯尽在精英留学站!
 
上一篇:砺志PMP模拟题每周精选3
下一篇:砺志PMP模拟题每周精选1
 相关新闻
·项目管理:PMP模拟题精选5·PMI-PMPExamTipsandNotes
·PMI-PMPExamTipsandNotes2·PMI-PMPExamTipsandNotes3
·PMI-PMPExamTipsandNotes4·PMI-PMPExamTipsandNotes5
·PMI-PMPExamTipsandNotes6·PMI-PMPExamTipsandNotes7
·PMI-PMPExamTipsandNotes8·PMI-PMPExamTipsandNotes9
·PMI-PMPExamTipsandNotes10·PMP美国项目管理认证考试模拟题精选6
·PMP美国项目管理认证模拟题精选7·PMP美国项目管理模拟题精选8
·PMP美国项目管理认证考试的模拟题精选10·砺志PMP模拟题每周精选1
 
◇ 重点栏目导航
◇ 精英服务承诺
教育顾问:010-51660910
QQ交流:138660910
相关资料
·2007年CPA考试《税法》讲义
·2008年10月自考笔记之《古代文学史一》(
·2008年10月自考笔记之《古代文学史一》(
·2008年10月自考笔记之《金融法》三
·2008年10月自考笔记之《金融法》二
·2008年10月自考笔记之《金融法》一
·新托福听力考试文化背景资料下载
·2008年1月至3月新托福考试口语资料整合
·北京大学2008年高考招生计划(医学)
·北京大学2008年高考招生计划(文科)
相关试题
·PMP模拟题精选10
·PMP模拟题精选9
·PMP模拟题精选8
·PMP模拟题精选7
·PMP模拟题精选6
·PMP模拟题精选5
·PMP模拟题精选5
·PMP模拟题精选4
·PMP模拟题精选3
·PMP模拟题精选2
相关热贴
·CGA入学条件及方法
·2007年度注册设备监理师执业资格考试报考
·上海紧缺人才岗位资格证书--AUTC现代物流
·教师资格考试心理学题库
·新托业考试面世,各媒体广泛关注
·监理考试读书心得--经验之谈
·2007年度注册资产评估师执业资格考试时间
·全国监理工程师执业资格考试大纲(2007)
·社会上的证书太多了,到底有没有作用呀?
·2007年度注册资产评估师执业资格考试报考