Qustions 1:
According to McGregor, a manager who uses Theory X sees workers as--
a.
Highly motivated,willing to take responsibility, and reliable
b. Highly untrustworthy, needing to be watched and closely managed at all times
c. Very productive when first given an assignment
d. Unproductive at first, followed by periods of high productivity
Qustions 3:
A Project management information system comprises--
a.
IAny of the project management software used for schedule development
b. All the requited reports to be prepared on the project, who receives each one, and the method of distribution
c. The policies and procedures to follow as the project is performed
d. The tools and techniques used to gather, integrate, and disseminate the output of the other project management processes
Qustions 5:
The Project plan should be distributed to--
a. All stakeholders in the performing organization
b. All project stakeholders
c. Project team members and the project sponsor
d. Those people defined in the communication management plan
Qustions 2:
Although an output of the various control processes, corrective action is also an input to project plan execution because it--
a. Ensures that project objectives are met
b. Expedites actions to ensure that activities are completed on time
c. Completes the feedback loop needed to ensure effective project management
d. Involves performing a planned reponse for a specific project risk event
Qustions 4:
A change control board is --
a. Recommended for use on all projects, large or small
b. Used as required to approve or reject change requests
c. Managed by the project manager who serves its secretare
d. Composed of key members of the project team
Qustions 6:
Leadership and management are both necessary on projects. One definition of managing is that it involves producing key results expected by stakeholders, whereas leadership involves --
a. Establishing direction, aligning people, and motivating and inspiring others
b. Getting things done through other people
c. Using charismatic power to motivate others to be productive
d. Using all types of power, as appropriate, as motivational tools
下一篇:PMP考试样题1(中文)
1. 你们公司为其
项目管理专业人员建立了一个奖励与表彰系统。项目成本绩效被用来为确定是否给予奖励的一个标准。你应该怎样做才能确保奖励反映真实的绩效?
a. 把加班算作工作的一部分
b. 制定成本基准计划
c. 利用挣值管理对绩效进行监测
d. 将可控制成本与不可控制成本分开来估算与预算
2.你在某家著名的医药公司工作。你们公司有很多项目机会,没有足够的资源来完成这些项目。你正领导着一个团队,来确定对项目进行选择并排定其优先次序的方法...[
查看详情]