Qustions 1:   
According to McGregor, a manager who uses Theory X sees workers as--   

a.   
Highly motivated,willing to take responsibility, and reliable   
b. Highly untrustworthy, needing to be watched and closely managed at all times   
c. Very productive when first given an assignment   
d. Unproductive at first, followed by periods of high productivity   

Qustions 3:  

A Project management information system comprises--  

a.   
IAny of the project management software used for schedule development   
b. All the requited reports to be prepared on the project, who receives each one, and the method of distribution   
c. The policies and procedures to follow as the project is performed   
d. The tools and techniques used to gather, integrate, and disseminate the output of the other project management processes   

Qustions 5:  

The Project plan should be distributed to--  

a.  All stakeholders in the performing organization  

b. All project stakeholders   
c. Project team members and the project sponsor   
d. Those people defined in the communication management plan   
   
Qustions 2:   
Although an output of the various control processes, corrective action is also an input to project plan execution because it--   
a. Ensures that project objectives are met   
b. Expedites actions to ensure that activities are completed on time   
c. Completes the feedback loop needed to ensure effective project management   
d. Involves performing a planned reponse for a specific project risk event   

Qustions 4:  

A change control board is --  

a. Recommended for use on all projects, large or small   
b. Used as required to approve or reject change requests   
c. Managed by the project manager who serves its secretare   
d. Composed of key members of the project team   

Qustions 6:  

Leadership and management are both necessary on projects. One definition of managing is that it involves producing key results expected by stakeholders, whereas leadership involves --   

a.  Establishing direction, aligning people, and motivating and inspiring others   
b.  Getting things done through other people  
c.  Using charismatic power to motivate others to be productive   
d.  Using all types of power, as appropriate, as motivational tools

下一篇:PMP考试样题1(中文)

1. 你们公司为其项目管理专业人员建立了一个奖励与表彰系统。项目成本绩效被用来为确定是否给予奖励的一个标准。你应该怎样做才能确保奖励反映真实的绩效?
a. 把加班算作工作的一部分
b. 制定成本基准计划
c. 利用挣值管理对绩效进行监测
d. 将可控制成本与不可控制成本分开来估算与预算
2.你在某家著名的医药公司工作。你们公司有很多项目机会,没有足够的资源来完成这些项目。你正领导着一个团队,来确定对项目进行选择并排定其优先次序的方法...[查看详情]

  影视动画培训   北大BEC培训官方报名网站   2008美国夏令营启航官方指定报名网站   2008留学第一站!  
  北师大 火星时代
共举影视动画培训之鼎
  北大BEC培训官方报名网站
现在报名独享95折!
  2008年国家职业资格考试
一次过关完全备考手册
  2008留学第一站
留学资讯尽在精英留学站!
 
上一篇:项目管理:PMP模拟题精选3
下一篇:PMP考试样题1(中文)
 相关新闻
·PMP项目人力资源管理复习要点·PMP项目质量管理复习要点
·PMP项目费用管理复习要点·PMP项目范围管理复习要点
·PMP项目时间管理复习要点·PMP项目总体管理复习要点
·PMP考试的10Do和10Don’t·PMP美国项目管理认证考试模拟试题
·ProjectCommunicationsManagement·ProjectCostManagement
·PMP认证考试——一壶永远烧不开的温吞水·PMP美国项目管理认证样题1
·PMP美国项目管理认证样题2·PMP美国项目管理认证样题3
·PMP美国项目管理认证样题4·PMP考试样题1(中文)
 
◇ 重点栏目导航
◇ 精英服务承诺
教育顾问:010-51660910
QQ交流:138660910
相关资料
·2007年CPA考试《税法》讲义
·2008年10月自考笔记之《古代文学史一》(
·2008年10月自考笔记之《古代文学史一》(
·2008年10月自考笔记之《金融法》三
·2008年10月自考笔记之《金融法》二
·2008年10月自考笔记之《金融法》一
·新托福听力考试文化背景资料下载
·2008年1月至3月新托福考试口语资料整合
·北京大学2008年高考招生计划(医学)
·北京大学2008年高考招生计划(文科)
相关试题
·PMP模拟题精选10
·PMP模拟题精选9
·PMP模拟题精选8
·PMP模拟题精选7
·PMP模拟题精选6
·PMP模拟题精选5
·PMP模拟题精选5
·PMP模拟题精选4
·PMP模拟题精选3
·PMP模拟题精选2
相关热贴
·CGA入学条件及方法
·2007年度注册设备监理师执业资格考试报考
·上海紧缺人才岗位资格证书--AUTC现代物流
·教师资格考试心理学题库
·新托业考试面世,各媒体广泛关注
·监理考试读书心得--经验之谈
·2007年度注册资产评估师执业资格考试时间
·全国监理工程师执业资格考试大纲(2007)
·社会上的证书太多了,到底有没有作用呀?
·2007年度注册资产评估师执业资格考试报考