Processes required to ensure the project is completed within the approved budget
|
Process |
Inputs |
Tools |
Outputs |
|
Resource Planning |
WBS
Scope Statement
Historical Information
Resource Pool Description
Organizational Policies
|
Expert Judgement
Alternatives Identification |
Resource Requirements |
|
Cost Estimating |
WBS
Resource Requirements
Resource Rates
Activity Duration Estimates
Historical Information
Chart of Accounts |
Analogous Estimating
Parametric Modeling
Bottom-Up Estimating
Computerized Tools |
Cost Estimates
Supporting Detail
Cost Management Plan |
|
Cost Budgeting |
WBS
Cost Estimates
Project Schedule |
Cost Estimating Tools/Techniques |
Cost Baseline
|
|
Cost Control |
Cost Baseline
Performance Reports
Change Requests
Cost Management Plan |
Cost Change Control System
Performance Measurement
Additional Planning
Computerized Tools |
Revised Cost Estimates
Budget Updates
Corrective Action
Lessons Learned
Estimate At Completion |