Which of the following is not a Project Management Knowledge Area
Communications Management
Procurement Management
Change Control Management
Project Integration Management
A project is a _____________ effort undertaken to create a _____________ product or service.
unique, temporary
significant, necessary
organized, profitable
temporary, unique
Possible socioeconomic influences on the project include
Budgetary considerations
Internationalization
Activity based costing
Matrix organization
Based on the life cycle model of the typical project, which stage is expected to experience the highest resource usage?
Initial phase(s)
Intermediate phase(s)
Closing phase(s)
Staffing phase(s)
Which is not a facilitating process?
Solicitation planning
Quality planning
Communications planning
Resource planning
Core processes:
Can interact differently with one-another, depending on the nature of the project
Have clear dependencies
Must be preformed simultaneously
Are managed by the same staff members throughout the project
Which of the following is a tool or technique used in integrated change control
Organizational procedures
Performance reports
Project plan updates
Performance measurement
The project plan:
Is a management control that will change only intermittently and only in response to an approved scope change
Usually includes the work break down structure but not major milestones
Is used to manage project execution
Includes open issues, but not pending decisions
Change control requests:
Must be relayed in writing
Provide the baseline against which changes will be controlled
Are always initiated externally
Are inputs to integrated change control
_________ is the formal procedure for sanctioning project work to ensure it is done at the right time.
Work-authorization system
Organizational procedures
Status review
Project planning
Which of the following is not a tool or technique of project plan execution?
PM Information system
Change control system
Organizational procedures
General management skills
Which scope management process creates the WBS?
Initiation
Scope planning
Scope definition
Scope verification