Project Cost Management (Level of difficulty: 4 / 10) Try to understand and remember the formulas! Resource Planning - determine the resource requirement Cost Estimating - understand the differences between the tools and techniques Cost Budgeting - what is the cost baseline for? Cost Control - what is earned value management? Don’t worry too much about earned value calculation. Rather straightforward. Try to understand the concept and logic behind the theory. Formulas: CV = EV - AC SV = EV - PV CPI = EV / AC SPI = EV / PV EAC = BAC / CPI (no variance) EAC = AC + ETC (assumptions were fundamentally flawed) EAC = AC + (BAC - EV) (variances are atypical and similar variances will not occur) EAC = [AC + (BAC - EV) /CPI ] (variances are typical and will change)