Disclaimer: These questions are intended for study purposes only. Success on these questions is not indicative of success on the Project Management Professional Certification Examination. This download of the Sample Exam Questions is for your personal use and NOT FOR commercial use. Any unauthorized use or duplication of this document is prohibited!
1. A narrative description of products or services to be supplied under contract is called:
a. The project plan.
B. A statement of work.
C. An exception report.
D. A Pareto analysis.
2. An example of scope verification is:
a. Reviewing the performance of an installed software module.
B. Managing changes to the project schedule.
C. Decomposing the WBS to a work package level.
D. Performing a benefit/cost analysis to determine if we should proceed with the pro
3. Which of the following is not an example of a source of scope change?
A. A variation in government regulations.
B. Failure to include a required feature in the design of a telecommunication system.
C. A need to engage in bottom-up cost estimating.
D. Introducing technology that was not available when scope was originally defined.
4. The subdivision of major project deliverables, as identified in the scope statement, into smaller, more manageable components is called:
a. Parametric estimation.
B. Scope definition.
C. Feasibility analysis.
D. Benefit-cost analysis.
5. The process of establishing clear and achievable objectives, measuring their achievement, and adjusting performance in accordance with the results of the measurement is called:
a. Strategic planning.
B. Alternative objectives inventory.
C. Management by objectives.
D. Contingency planning.
6. Configuration management is:
a. Used to ensure that the description of the project product is correct and complete.
B. The creation of the work breakdown structure.
C. The set of procedures developed to assure that project design criteria are met.
D. A mechanism to track budget and schedule variances.
7. A fundamental tenet of modern quality management holds that quality is most likely to be achieved by:
a. Planning it into the project.
B. Developing careful mechanisms to inspect for quality.
C. Striving to do the best job possible.
D. Conducting quality circle activities.
8. Your most recent project status report contains the following information: BCWP = 3,000, ACWP = 3,500, and BCWS = 4,000. The schedule variance is:
a. + 1,000.
B. + 500.
C. - 500.
D. - 1,000.
9. Learning curve theory emphasizes that in producing many goods:
a. Cost decreases as production rates increase.
B. Average unit cost decreases as more units are produced.
C. Materials become cheaper when they are purchased in bulk.
D. Laborers become more productive because of technological advances.
10. Rearranging resources so that constant resource levels are maintained is called:
a. Floating. 
B. Leveling.
C. Restructuring.
D. Crashing.

本新闻共2页,当前在第1页  1  2

  影视动画培训   北大BEC培训官方报名网站   2008美国夏令营启航官方指定报名网站   2008留学第一站!  
  北师大 火星时代
共举影视动画培训之鼎
  北大BEC培训官方报名网站
现在报名独享95折!
  2008年国家职业资格考试
一次过关完全备考手册
  2008留学第一站
留学资讯尽在精英留学站!
 
上一篇:PMP中文模拟题系列——范围管理10题
下一篇:PMP美国项目管理与MBA的比较
 相关新闻
·美国项目管理PMP认证模拟考试试题精选5·PMP国家职业资格认证11月鉴定模拟题(1)
·项目管理:IPMP与PMP的区别·PMP美国项目管理样题1
·PMP美国项目管理模拟样题2·PMP美国项目管理模拟样题3
·PMP美国项目管理认证的模拟考试的样题4·PMP美国项目管理认证的模拟考试的样题6
·PMP美国项目管理认证的模拟考试的样题5·PMP美国项目管理认证的模拟考试的样题7
·PMP美国项目管理认证的模拟考试的样题8·PMP美国项目管理认证的模拟考试的样题9
·PMP美国项目管理认证的模拟考试的样题10·PMP认证考试内容
·PMP美国项目管理与IPMP的比较·PMP美国项目管理与MBA的比较
 
◇ 重点栏目导航
◇ 精英服务承诺
教育顾问:010-51660910
QQ交流:138660910
相关资料
·2007年CPA考试《税法》讲义
·2008年10月自考笔记之《古代文学史一》(
·2008年10月自考笔记之《古代文学史一》(
·2008年10月自考笔记之《金融法》三
·2008年10月自考笔记之《金融法》二
·2008年10月自考笔记之《金融法》一
·新托福听力考试文化背景资料下载
·2008年1月至3月新托福考试口语资料整合
·北京大学2008年高考招生计划(医学)
·北京大学2008年高考招生计划(文科)
相关试题
·PMP模拟题精选10
·PMP模拟题精选9
·PMP模拟题精选8
·PMP模拟题精选7
·PMP模拟题精选6
·PMP模拟题精选5
·PMP模拟题精选5
·PMP模拟题精选4
·PMP模拟题精选3
·PMP模拟题精选2
相关热贴
·CGA入学条件及方法
·2007年度注册设备监理师执业资格考试报考
·上海紧缺人才岗位资格证书--AUTC现代物流
·教师资格考试心理学题库
·新托业考试面世,各媒体广泛关注
·监理考试读书心得--经验之谈
·2007年度注册资产评估师执业资格考试时间
·全国监理工程师执业资格考试大纲(2007)
·社会上的证书太多了,到底有没有作用呀?
·2007年度注册资产评估师执业资格考试报考