1.  Communications  is  best  described  as:  
A.  an  exchange  of  information.  
B.  providing  written  or  oral  directions.  
C.  consists  of  senders  and  receivers  
D.  effective  listening.  
E.  All  of  the  above  
ANS:  E  

2.  Fixed  Price  contracts  place  more  risk  on  the:  
A.  owner  
B.  buyer  
C.  seller  
D.  contractor  
E.  C  or  D  
ANS:  E  

3.  Life  cycle  costing  is  the  total  cost  to  the  customer  for  the  
acquisition  and  ownership  over  its  full  life.  Life  cycle  costing  
categories  include  the  cost  
of  _____,  _____,  and  _____.  
A.  R  &  D,  maintainability,  operation  and  support.  
B.  R  &  D,  production,  operation  and  support.  
C.  Acquisition,  operations,  maintenance.  
D.  Production,  operations,  maintenance.  
E.  None  of  the  above  
ANS:  B  

4.  Management  By  Objectives  assumes  that  the  team:  
A.  is  receptive  to  an  unstructured  environment.  
B.  does  not  require  close  supervision.  
C.  possesses  a  self  directed  philosophy  
D.  identifies  with  project  objectives.  
E.  All  of  the  above.  
ANS:  E  

5.  Quality  may  be  defined  as:  
A.  conformance  to  requirements.  
B.  fitness  for  use.  
C.  continuous  improvement  of  products  and  services  
D.  appeal  to  the  customer  
E.  All  of  the  above  except  B  
ANS:  E  

6.  Since  risk  is  associated  with  most  projects,  the  best  course  of  
action  is  to:  
A.  cover  all  project  risks  by  buying  appropriate  insurance  
B.  ignore  the  risks,  since  nothing  can  be  done  about  them  and  move  
forward  with  the  project  in  an  expeditious  manner.  
C.  avoid  projects  with  clear  and  present  risks  
D.  eliminate  all  known  risks  prior  to  the  execution  phase  of  the  
project  
E.  identify  various  risks  and  implement  actions  to  mitigate  their  
potential  impact  
ANS:  E  

7.  The  process  of  choosing/documenting  the  best  approach  to  achieve  
the  project  objectives  is  part  of:  
A.  The  scope  baseline.  
B.  Scope  authorization  
C.  Scope  definition  
D.  Scope  planning.  
E.  All  of  the  above.  
ANS:  D  

8.  Time  management  is  the  allocation  of  time  in  a  project’s  life  
cycle  through  the  process  of:  
A.  Planning  
B.  Estimating.  
C.  Scheduling.  
D.  Controlling  
E.  All  of  the  above.  
ANS:  E  

9.  A  comprehensive  definition  of  scope  management  would  be:  
A.  Managing  a  project  in  terms  of  its  objective  through  the  concept,  
development,  implementation,  and  termination  phases  of  a  project.  
B.  Approval  of  the  scope  baseline.  
C.  Approval  of  the  detailed  project  charter.  
D.  Configuration  control.  
E.  Approved  detailed  planning  including  budgets,  resource  allocation,  
linear  responsibility  charts  and  management  sponsorship.  
ANS:  A  

10.  Cost  Plus  Percentage  of  Cost  contracts  are  more  desirable  for  
the:  
A.  owner  
B.  buyer  
C.  seller  
D.  contractor  
E.  C  or  D  
ANS:  E  

下一篇:PMP美国项目管理模拟样题3

1.You  are  a  project  manager  for  Waterways  Houseboats,  Inc.  You’re  
been    asked  to  perform  a  benefit/cost    analysis  for  two  proposed  
projects.  Project  A  costs  $2.4&n...[查看详情]

  影视动画培训   北大BEC培训官方报名网站   2008美国夏令营启航官方指定报名网站   2008留学第一站!  
  北师大 火星时代
共举影视动画培训之鼎
  北大BEC培训官方报名网站
现在报名独享95折!
  2008年国家职业资格考试
一次过关完全备考手册
  2008留学第一站
留学资讯尽在精英留学站!
 
上一篇:PMP美国项目管理认证的模拟考试的样题6
下一篇:PMP美国项目管理模拟样题3
 相关新闻
·什么是CAPM(CertifiedAssociateinProjectManagement)·项目管理专业助理师(CAPM)资格认证
·CAPM认证在国内首次考试将于2006年6月24日举行·项目管理专业助理师(CAPM)资格认证考试注意事项
·CAPM考试内容及计分方法·项目管理:CAPM报名流程
·项目管理助理师(CAPM)中文报名表下载·项目管理助理师(CAPM)CAPMHandbook
·美国项目管理PMP认证模拟考试试题精选3·美国项目管理PMP认证模拟考试试题精选4
·美国项目管理PMP认证模拟考试试题精选5·PMP国家职业资格认证11月鉴定模拟题(1)
·项目管理:IPMP与PMP的区别·PMP美国项目管理样题1
·PMP美国项目管理模拟样题2·PMP美国项目管理模拟样题3
 
◇ 重点栏目导航
◇ 精英服务承诺
教育顾问:010-51660910
QQ交流:138660910
相关资料
·2007年CPA考试《税法》讲义
·2008年10月自考笔记之《古代文学史一》(
·2008年10月自考笔记之《古代文学史一》(
·2008年10月自考笔记之《金融法》三
·2008年10月自考笔记之《金融法》二
·2008年10月自考笔记之《金融法》一
·新托福听力考试文化背景资料下载
·2008年1月至3月新托福考试口语资料整合
·北京大学2008年高考招生计划(医学)
·北京大学2008年高考招生计划(文科)
相关试题
·PMP模拟题精选10
·PMP模拟题精选9
·PMP模拟题精选8
·PMP模拟题精选7
·PMP模拟题精选6
·PMP模拟题精选5
·PMP模拟题精选5
·PMP模拟题精选4
·PMP模拟题精选3
·PMP模拟题精选2
相关热贴
·CGA入学条件及方法
·2007年度注册设备监理师执业资格考试报考
·上海紧缺人才岗位资格证书--AUTC现代物流
·教师资格考试心理学题库
·新托业考试面世,各媒体广泛关注
·监理考试读书心得--经验之谈
·2007年度注册资产评估师执业资格考试时间
·全国监理工程师执业资格考试大纲(2007)
·社会上的证书太多了,到底有没有作用呀?
·2007年度注册资产评估师执业资格考试报考